Olara, the Resort Rising on the West Palm Beach Waterfront

New Developments

Olara, the Resort Rising on the West Palm Beach Waterfront

Nikko Karki
Nikko Karki September 13, 2026
North Flagler Drive leaves downtown West Palm Beach and runs up the water toward Northwood, past the stretch where the Intracoastal opens to its widest point. A concrete tower now stands eighteen floors above that stretch, with eight to go and a 2028 delivery target. The name on the site is Olara. The company behind it spent three decades buying and building in Manhattan, mostly office and mixed use, and has never built in South Florida before. This report covers the developer, the concept it brought south, and what the project offers buyers this fall.
Residences
275
On about four waterfront acres at 1919 N Flagler Drive, with 170 rentals in a second tower
Floors
18 of 26
Where the developer reports construction this month, two years from delivery
Amenities
80,000 SF
The program Arch Amenities will run, with José Andrés cooking and Sollis Health on call
The Entry
From $1.7M
The developer's stated starting price. Asking, with no recorded closings yet

Three Decades in Manhattan, Then This

Savanna was founded in New York in 1992 by Christopher Schlank and Nicholas Bienstock. Over thirty years the firm has invested in and developed more than 17 million square feet, primarily across New York City's five boroughs. Its record runs mostly to Manhattan office and mixed use buildings. Olara is the firm's first project in South Florida, and the firm chose a four acre waterfront site over a downtown one. Both facts shape what is going up.

The capital is institutional. Savanna closed construction financing in March 2025, in a loan reported at $380 million. The lender group includes Zeckendorf Development, Sculptor Real Estate, One Investment Management and Octo Capital. The Mactaggart Family Partnership, a family investor with more than a century in real estate, is a capital partner. SavCon and Gilbane hold the construction contract, and Compass Development Marketing Group runs sales for the developer.

The design team is easier to place locally. Arquitectonica drew the building under founder Bernardo Fort-Brescia, with floor plates set to hold water views on more than one side. The same firm is designing The Berkeley near downtown. Gabellini Sheppard Associates designed the interiors, and EDSA the waterfront gardens.

A Residential Tower Run Like a Resort

The concept is service at a scale condominiums rarely attempt. Nearly 80,000 square feet of amenity space fills the base and the deck, and the developer hired operators rather than promising owners would figure it out. Arch Amenities Group, the operator behind the Baccarat residences in New York and the Eau Spa in Manalapan, manages the program year round. The wellness floors carry 13,000 square feet of fitness space designed with The Wright Fit, plus a Japanese style onsen, cold plunge pools and meditation rooms. A Sollis Health membership puts medical concierge care in the building.

The restaurant is the headline hire. José Andrés takes 8,500 square feet on the water for his first restaurant in the Palm Beaches, open to the public, with priority reservations and in-residence dining for owners. His team will also run food service across the amenity spaces. A private marina with six slips sits at the seawall, and a full building generator serves every residence, which matters on a coast that loses power in storms.

The homes themselves run from about 1,500 to more than 4,200 square feet, from two bedroom plus den plans up to penthouses with private rooftops. A second tower behind the condominium holds the rental apartments, which keeps leases out of the owners' building. The chart below holds the three published categories.

Three Products in One Tower
The published residence categories by interior size. Penthouses add private rooftop space above the stated range.
Olara's three residence categories by interior square footage1,000 SF2,000 SF3,000 SF4,000 SFTwo Bedroom + Den1,4771,800Three Bedroom + Den2,2003,000Penthouse Collection3,5004,097Olara's three residence categories by interior square footage1,000 SF2,000 SF3,000 SF4,000 SFTwo bed + denThree bed + denPenthouses
  • Two bedroom + den · 1,477 to 1,800 SF, the entry tier
  • Three bedroom + den · 2,200 to 3,000 SF
  • Penthouses · 3,500 to 4,097 SF plus private rooftops

The developer's published floor plan categories per our building page, September 2026, subject to change. The stated entry price applies to the smallest tier.

Eight floors remain between the buyers and the keys.

Past the Two-Thirds Mark

Construction began in March 2024, and the dock went in first. Vertical work reached the podium in late 2025, and the developer's site this month reports concrete at the 18th floor of the planned 26. Delivery is expected in 2028. The usual caution applies to every date on a construction schedule, and the purchase contract's outside date matters more than the marketed year. Still, a buyer here is no longer judging a rendering. The building exists, and its remaining risk is finish and schedule rather than whether a tower rises at all.

Four Dated Facts and a Target
The construction calendar the developer has published, from the March 2024 groundbreaking to the 2028 delivery target. The tower reached its 18th floor this month.
Olara's published construction milestones, March 2024 groundbreaking through the 2028 delivery target20242025202620272028GroundbreakingMarch 2024Financing closedMarch 2025Vertical startLate 202518th floorSeptember 2026Delivery target2028Olara's published construction milestones, March 2024 groundbreaking through the 2028 delivery targetGroundbreaking2024Financing closed2025Vertical start202518th floor2026Delivery target2028PUBLISHED MILESTONES, IN ORDER
  • Reported this month: concrete at the 18th of 26 floors
  • Financing closed March 2025, reported at $380M

The developer's published materials and press releases via olarawestpalmbeach.com, September 2026. Delivery dates on any construction schedule are targets, not commitments.

What the Money Buys Before Delivery

Savanna prices from a stated $1.7 million, which opened below the corridor's other new towers. Two bedroom plus den plans of roughly 1,500 square feet are the entry tier. Every published number at this stage is an asking price. Closings begin at delivery, so nothing has been recorded and no resale ledger exists to check the pricing against.

One residence is on the multiple listing service (MLS) this week. Residence 911, a three bedroom of 2,358 square feet, asks $3.37 million. Developer inventory and early resales move quietly at this stage, so the public feed understates what can be bought. Two open questions belong on any buyer's checklist. Association fees are not final while sales run, and the declaration that will set rental rules has not been published. Our companion guide, Before You Buy at Olara, covers the contract and the review window in detail.

The North Waterfront Fills In

Three other projects define the waterfront around the site, and the four make more sense read together. Two blocks south at 1745 North Flagler, the Ritz-Carlton Residences offers 138 branded homes asking from $3 million, also for 2028. Alba, north at 4714 in Northwood, delivered first. Closings have begun there, and its page counts eight recorded sales in the trailing twelve months. Farther up the water, above the Lake Park marina, Nautilus 220 opened in March 2026, more than ninety percent sold. Its first resales have recorded between $1.28 million and $3 million.

Read the bases carefully when comparing. Olara and the Ritz-Carlton project quote asking prices for unfinished buildings, while Alba and Nautilus 220 now have recorded closings. Our county development map puts the whole field on one page, our study of the district projects compares the formats, and the pipeline page tracks every delivery. The West Palm Beach guide covers the city around them.

The North Waterfront, Priced on Two Bases
The new projects north of downtown in street order. Two quote asking prices for unfinished buildings, and two have recorded closings.
The north Intracoastal waterfront in street order, four new condominium projects with their price basesTHE INTRACOASTAL · PALM BEACH AND THE INLET OPPOSITERitz-Carlton1745 N FlaglerAsking from $3M3 open · $9.7M listOlara1919 N FlaglerFrom a stated $1.7M18th floor · 2028Alba4714 N FlaglerClosings begun8 sales, trailing yearNautilus 220Lake Park marinaOpened March 2026Resales to $3MDOWNTOWN · SOUTHLAKE PARK · NORTHThe north Intracoastal waterfront in street order, four new condominium projects with their price basesTHE INTRACOASTAL · PALM BEACH AND THE INLET OPPOSITERitz-CarltonAsking from $3M · no closingsOlaraFrom a stated $1.7M · no closingsAlbaClosings begun · 8 sales TTMNautilus 220Opened 2026 · resales to $3MSOUTH TO NORTH, TOP TO BOTTOM
  • Olara · from a stated $1.7M, tower at the 18th floor
  • Ritz-Carlton Residences asking from $3M · Alba 8 recorded sales TTM · Nautilus 220 opened March 2026

Each project's page on this site, September 2026. Olara and Ritz-Carlton Residences figures are asking prices with no recorded closings. Alba and Nautilus 220 have begun recording sales.

The four projects, side by side
The north waterfront's new condominium field, from each project's page on this site.
← Scroll to see all columns →
ProjectHomesStoriesStatusOpenMedian list
Olara27526Delivery 20281$3.4M
Ritz-Carlton Residences13827Delivery 20283$9.7M
Alba5522Closings begun4$3.4M
Nautilus 220330Twin 24Opened March 20261$1.4M

Building pages on this site, September 2026. Open listings and median list prices are the pages' live MLS feeds. Developer inventory sells outside the feed, so counts are floors.

What each project includes
The amenity programs, from each project's page on this site.
← Scroll to see all columns →
ProjectWaterWellness & serviceDistinct
OlaraSix slip private marina, lap and leisure poolsArch Amenities program, Wright Fit fitness, Sollis HealthJosé Andrés restaurant, full building generator
Ritz-Carlton ResidencesIntracoastal frontageRitz-Carlton managed services, butler and porter serviceCove Club membership, Marriott Bonvoy enrollment
AlbaResident dockage on the Intracoastal, dual poolsMount Sinai medical conciergeNorthwood's first luxury waterfront building

Amenity details per each building page, September 2026. Developers change offerings before delivery, so verify current terms in the purchase documents.

Olara rendered at dusk on the West Palm Beach waterfront
The tower as rendered from the water, with the amenity levels at the base and the rental building behind. Rendering: Savanna.

Bottom Line

The developer is new to Florida, and the concept is not subtle. Olara wraps a resort scale service program around homes priced to open beneath the corridor's branded towers, and the building itself is past the two-thirds mark. The operators are hired, the financing is closed and the calendar is public. What no one can show yet is a recorded price, because closings start at delivery. Until then the proven buildings nearby supply the reference points, and the construction schedule is the fact to watch.

Before you visit the gallery: Read the corridor's other pages first. The conversation is sharper when you walk in knowing what the finished buildings nearby have recorded.

Ask About Olara

Project facts, pricing and dates follow the developer's published materials and our Olara building page as cached on September 14, 2026. All of it is subject to change. The developer and its sales agent publish the stated entry price. Every price in this report is an asking price, and no closing has been recorded at the project. The construction loan amount is the figure reported across the financing press in March 2025.

Corridor figures for Alba, the Ritz-Carlton Residences and Nautilus 220 come from their pages on this site on the same date. Open listing counts and median list prices are live MLS feeds, which developer inventory does not enter, so counts are floors.

This is market data and public record analysis, not investment advice.

palmbeachluxury.com building pages for Olara and for Alba Palm Beach, The Ritz-Carlton Residences West Palm Beach and Nautilus 220, all cached September 14, 2026.

The developer's official site, olarawestpalmbeach.com, including its published press index, September 2026.

Palm Beach Luxury: the county new development map and the Nora House corridor study.

Nikko Karki
Written by

Nikko Karki

Nikko Karki has worked in real estate for nearly two decades, beginning on the developer side at Related Group in West Palm Beach, then through private real estate investments and cross-border M&A across the U.S., Europe, and Southeast Asia. He holds an M.Sc. in economics from the Helsinki School of Economics. He built Palm Beach Luxury to make his analysis available to anyone in the market, for free.
About our team →
Frequently Asked Questions
Olara is a 26 story condominium tower of 275 residences under construction at 1919 N Flagler Drive, on about four acres of West Palm Beach Intracoastal frontage. New York developer Savanna is building its first South Florida project here, with nearly 80,000 square feet of amenities, a six slip marina and a José Andrés restaurant. A second tower holds 170 rental apartments.
The developer prices from a stated $1.7 million for two bedroom plus den residences of about 1,500 square feet. One resale listing is on the MLS asking $3.37 million. No closing has been recorded because the building delivers in 2028, so every published figure is an asking price. Contact the developer's gallery or our team for current pricing.
Delivery is expected in 2028. Construction began in March 2024, vertical work reached the podium in late 2025, and the developer reported the tower at the 18th of 26 floors in September 2026. Dates on a construction schedule are targets, and the purchase contract's outside date is the binding one.
Savanna, a New York real estate firm founded in 1992 by Christopher Schlank and Nicholas Bienstock, is the developer, and Olara is its first South Florida project. Arquitectonica designed the building, Gabellini Sheppard the interiors, and SavCon and Gilbane are the general contractors. Construction financing closed in March 2025 with a reported $380 million loan.